With an extension of 32,000 m², the expansion of the Part-Dieu shopping center is an extraordinary project.
This highly technical project, given the quality of the subsoil and foundations, required the installation of 250 tons of TourEchaf on HEB load distribution profiles.
This was a delicate operation, as a total of 23 meters of shoring had to be erected.
The TourEchaf system was used to safely shore up the columns and beams on each level, five extensions.
Customer : GCC Construction & Léon Grosse